Two routes from site visit to energising, decided by your maximum demand. We handle the contractor route for homes, shoplots and workshops up to 100A — load calculation, wiring to MS IEC 60364, Form G and Form H, myTNB submission, metering and handover. Above 100A we work alongside your consultant engineer on the installation, testing and meter application.
Process guide
Is your load up to 100A?
About 72 kVA on three phase, whole-current metering. Most homes, shoplots, offices and small workshops stay on the contractor route. Large commercial buildings, factories and plants above 100A take the consultant route.
Homes, shoplots & small workshops
Appoint a registered electrical contractor (registered with Suruhanjaya Tenaga). We handle this route end to end.
- Site visit and load calculation — list connected load, estimate maximum demand, pick the application type.
- Wiring, testing and certificates — installation to MS IEC 60364; Form G (completion) and Form H (test) issued.
- Submit on myTNB — signed application form, owner documents, certificates, site photos and location map.
- TNB issues connection charge statement — within 14 days for individual domestic applications (TNB Customer Charter).
- Pay connection charge, deposit and RM10 stamp duty — online via myTNB or at Kedai Tenaga.
- TNB installs meter and connects supply — contractor present at energising.
Large commercial & factories
Appoint an electrical consultant engineer registered with the Board of Engineers Malaysia — one per application, by letter. We handle the installation, testing and meter application alongside your consultant.
- Part A: development plan to local authority / OSC (TNB comments within 14 days per round; approval valid 2 years).
- Part B: supply application on myTNB with SLD, load summary, power quality declaration and CT metering details.
- TNB system study and joint meeting — agree substation, cable route, metering and meter location.
- Pay connection charges after TNB’s Notice of Connection Charges.
- Build and hand over substation — land and building to TNB at RM10 nominal value, with CCC; TNB equips and commissions.
- Meter application and energising — contractor applies for meter; Electrical Testing Engineer present for MV/HV.
Scope
What we handle
Application & documentation
Prepared and submitted for you
- Load calculation & maximum demand assessment
- Single-line diagram (SLD) & wiring layout
- Form G (completion) & Form H (test) certificates
- New supply, additional supply & 1-to-3-phase upgrade forms on myTNB
- Liaison with TNB throughout the process
Metering & connection
Coordinated with TNB
- Meter position photos & nearest TNB supply point
- Single-phase & three-phase whole-current metering
- CT metering for larger loads, where applicable
- Contractor present at energising
Testing & handover
Documented and signed off
- Installation to MS IEC 60364
- Full test sequence before Form H
- Commissioning of the installation
- Labelled distribution board & completion documents
Who it’s for
When you need a supply application
New house or renovation
New account, added load, EV charger, or single-to-three-phase upgrade for a home.
Shoplot, office or restaurant
Commercial paperwork, non-domestic tariff and the 100A limit that changes the rules.
Factory or plant
Above 100A: consultant engineer, substation, maximum demand and longer lead times.
1-phase to 3-phase
Upgrading an existing single-phase supply to three phase — often paired with this application.
How we work
From load calculation to supply turn-on
Site visit & load calc
List connected load, estimate maximum demand, and pick the application type — new, additional or upgrade; up to 100A or above.
Quote & scope
An itemised quote covering the wiring work, documentation and the TNB application.
Wiring & certificates
Installation to MS IEC 60364. Form G (completion) and Form H (test) issued.
Submit on myTNB
Signed application form, owner documents, certificates, site photos and location map.
Pay, meter & energise
Connection charge, deposit and RM10 stamp duty. TNB installs the meter; we are present at energising.
On site
Metering & distribution ready for TNB
Neat meter boards, colour-coded DB wiring and tidy trunking make inspection and energising smoother.
Paperwork
Documents involved
You provide the premises-side paperwork. We prepare the technical documents — Form G, Form H, single-line diagram, location map and meter-position photos.
- Completed and signed TNB application form
- Copy of IC (or authorised person’s IC with company letter of authorisation)
- Proof of occupation: S&P pages, tenancy agreement, or land / strata title
- For businesses: Form 9 / Form D / JMB–MC certificate; landowner consent; development order where required
- Existing TNB bill or account number, for an upgrade
- List of major equipment and its ratings (load calculation)
Charges & timing
What you pay TNB — and how long it takes
Connection charge
Paid to TNB
- Based on the maximum demand you declare
- Plus cable charges if TNB extends its network to you
- Separate from your contractor’s fee
Deposit & stamp duty
At payment stage
- Deposit: two months of estimated electricity bills
- Stamp duty: RM10
- Pay online via myTNB or at Kedai Tenaga
Typical timelines
From complete application
- Domestic: connection charge statement within 14 days; meter within 5 working days of deposit (Customer Charter)
- LV without substation: under 3 months
- With substation: 3 to 12 months
FAQ
Frequently asked questions
Do I need a registered contractor to apply for TNB supply?
What is the 100A line?
How long does a TNB supply application take?
What do I pay TNB?
Can you handle the wiring and the TNB application together?
Insights
Read the guides for your premises type
Three supporting articles in the TNB supply application topic cluster.
Applying for TNB supply for a new house
Single vs three phase, documents, charges and the short homeowner checklist.
Shoplots, offices and restaurants
SSM papers, landowner consent, non-domestic tariff and the 100A limit.
Factories: substations & maximum demand
Consultant route, Part A/B approvals, voltage bands and lead times.
Related
Related services
Single-phase to 3-phase
1- to 3-phase upgrades, distribution boards & machine circuits — often paired with a supply application.
Electrical wiring & installation
New wiring and rewiring done to standard, ready for the certificate and inspection.
Power factor correction
Non-domestic and industrial sites need to keep power factor above 0.85 after connection.
Get a quote
Ask us about your TNB application
Fill in the short form — we open WhatsApp with your details prefilled. Or WhatsApp / call us directly.
New premises or adding load? Talk to us.